DESIGN BUILD FOR E&I INSTALLATION AT PELLET MILL FACILITY – WAWA, ON

Rentech retained EAD to perform the engineering, project management, construction management, and design to convert a decommissioned fiber mills into a wood pellet plant in Wawa, Ontario. Acting as the sub-contractor and adhering to all safety requirements, TESC completed the design build for the entire electrical and instrumentation installation at the Rentech Pellet Mill Facility in May 2015. TESC was responsible for cable tray and structures, cabling, terminations, equipment installation, commissioning, and expansion of an existing substation, which included an additional pole line complete with metering and tie-ins at the re-purposed plant that was designed to produce 400,000 metric tons annually.

In-house Services Rendered

Electrical