Lake Shore Gold Corp.

LAKE SHORE GOLD HOIST INSTALLATION – TIMMINS, ON

In the spring of 2007, TESC Contracting was invited to Lake Shore Gold’s site to conduct an assessment of the delayed installation of their nine and twelve-foot hoists. Upon completion, the civil portion of the project was immediately turned over to TESC where the team was able to create an accelerated schedule that met the client’s goals.

TESC’s Industrial Millwrighting Department assessed the hoists to be installed and presented an accelerated schedule which cut production time by 50% in comparison to its competitors’ proposals.

Not only was the project completed on time, but TESC Contracting manpower performed additional work which included extensive repairs and reconditioning to the two hoists during the installation process. Upon commissioning, the hoists passed certification without delay and were immediately placed into service.

Our experienced team and vast resources allow us to expedite projects and deliver a superior product for our clients every time.

In-house Services Rendered

Structural

Engineered Scaffolding

Millwrighting