Forestry and Agriculture

Domtar HD Tower Piping

Client / Owner

Domtar

Location

Espanola Mill,
Espanola, Ontario

Completion Date
October 2020
No items found.

Domtar HD Tower Piping

TESC was employed by Domtar to supply all labour, material, and equipment for the demolition, material supply/fabrication, and installation of the piping systems and removal of existing piping system to allow for routing of 2.5 configuration piping system at the Espanola Mill, in Espanola, Ontario.

The TESC team effectively executed the demolition, which included removal and/or temporary modifications of all existing piping, structural steel, and existing equipment required to accommodate the scope of work. The team then performed all associated structural, piping, mechanical, and engineered scaffolding installations.

Specifically, TESC was responsible for the following:

  • Installation of new structural roof support and pipe support steel
  • Removal of existing cladding on existing structural penthouse
  • Installation of new structural penthouse
  • Removal of existing redundant 24” piping system
  • Installation of new 24”, 12”, and 3” diameter 316L and 317L stainless steel pulp pipe systems
  • Installation of 8” stainless steel 316L flush line piping system
  • Installation of instrument air piping, tubing, and solenoids for valve control

TESC completed this work during a critical mill outage as part of Domtar’s 2.5 single line configuration and modernization project. TESC worked with Domtar to complete the scope during the planned outage duration. 

The project was successfully completed without injuries during the COVID-19 pandemic.

More Projects

Barrick Hemlo Cyanide Detox Plant & Tailings Flotation Complex
Glencore Onaping Depth Project Headworks Steel Installation
CKPI Installation of Chip Thickness Screening System
Domtar Power Recovery Boiler Chemical Treatment
Coniston Generating Station 22kV-44kV Conversion
Mistinikon Lake Replacement of Spillway Guardrails and Flashboards
McVittie Generating Station Roof Replacement
Detour Gold Corporation Detour Lake Mine 13.8kV Substation Installation
Northgate Minerals Young Davidson Mine Substation Installation
BHP Billiton Jansen Mine Freeze Plant Supply Installation
Detour Gold Corporation Detour Lake Mine Concrete Slabs
Northgate Minerals Young Davidson Mine Headframe Construction
BHP Billiton Jansen Mine Hoist House Buildings
Vale No.8 Converter Installation
Sudbury INO Process Gas Project, Phase I
Mosaic K3 Mine Service Shaft Headframe Construction
Vale No.10 Converter Installation
Vale Matte Sep SMPEI Phase 2
Vale Matte Sep SMPEI Phase 1
Harte Gold Sugar Zone Mill Installation SMPEI Project
Tahoe Bell Creek Shaft Sinking Project
Sudbury Lime Plant Electrical Services Installation
Glencore Concentrate Unloading

Our portfolio

Project highlights showcasing TESC’s capabilities, problem solving, and leadership across industries.