Mosaic K3 Mine Service Shaft Headframe Construction

TESC was engaged as subcontractor by Hatch to construct the Service Shaft Headframe at The Mosaic Company’s K3 Mine in Esterhazy, Saskatchewan. 

The scope of work involved the installation of structural steelwork for crane support, mezzanine, crash, arrester and Koepe sub-foundation floor levels, as well as for the Koepe house penthouse. Civil works included the installation of the Koepe penthouse composite roof, various floor levels and the concrete columns between Blair hoist level (150 feet) and arrester level (202 feet). Electrical works included the relocation of aircraft warning lights, installation of lighting for mosaic logos, as well as the supply and installation of lightning protection for the service shaft headframe penthouse. 

Working intensely during the winter months in the harsh Saskatchewan climate, the team was exposed to extreme cold weather conditions, which caused challenges building one of the world’s tallest mining headframes, standing at 374 feet. Nevertheless, the project was completed safely and cost effectively.

More Projects

Barrick Hemlo Cyanide Detox Plant & Tailings Flotation Complex
Glencore Onaping Depth Project Headworks Steel Installation
CKPI Installation of Chip Thickness Screening System
Domtar Power Recovery Boiler Chemical Treatment
Domtar HD Tower Piping
Coniston Generating Station 22kV-44kV Conversion
Mistinikon Lake Replacement of Spillway Guardrails and Flashboards
McVittie Generating Station Roof Replacement
Detour Gold Corporation Detour Lake Mine 13.8kV Substation Installation
Northgate Minerals Young Davidson Mine Substation Installation
BHP Billiton Jansen Mine Freeze Plant Supply Installation
Detour Gold Corporation Detour Lake Mine Concrete Slabs
Northgate Minerals Young Davidson Mine Headframe Construction
BHP Billiton Jansen Mine Hoist House Buildings
Vale No.8 Converter Installation
Sudbury INO Process Gas Project, Phase I
Vale No.10 Converter Installation
Vale Matte Sep SMPEI Phase 2
Vale Matte Sep SMPEI Phase 1
Harte Gold Sugar Zone Mill Installation SMPEI Project
Tahoe Bell Creek Shaft Sinking Project
Sudbury Lime Plant Electrical Services Installation
Glencore Concentrate Unloading

Our portfolio

Project highlights showcasing TESC’s capabilities, problem solving, and leadership across industries.