Vale No.10 Converter Installation

The general scope of work for this contract package covers the installation of mechanical, piping, electrical, and instrumentation for Vale’s Converter No. 10. The scope also includes miscellaneous steel (platforms, grating, stairs, and handrails), as well as some civil work.

The mechanical scope consisted of the following activities:

  • The fabrication and installation of the off-gas flues ductwork and dust collection ductwork;
  • The installation of the converter feed system with ploughs, chutes, feed conveyors, transfer conveyor and retractable feed chute;
  • The installation and alignment of the converter drive system;
  • The installation of the primary hood and the supply and installation of the secondary hood, including the actuating systems;
  • The installation of a lift gate system, GASPE puncher system, mouth cooling fans, pumps, hydraulic cylinders, mixed flow fan;
  • The installation of the drag conveyor system including hammer mill, blowpot and dust bagging station;
  • The installation of the converter control booth;
  • The installation of three air conditioning units and ductwork for the control booth as well as two switch rooms; and
  • The final setting and alignment of previously installed equipment including the converter, spray chamber, and the flux and scrap bins. The piping/instrumentation scope involved the following activities:
  • The fabrication and installation of over 12,000 linear feet of pipe from small bore up to 30”;
  • Installation of cooling water system, including cooling water pump room, heat exchangers, and primary cooling to converter hoods;
  • Installation of spray chamber and spray water piping system, including flow and control elements; Blast air, light oil/diesel, steam, oxygen, pneumatic, vacuum, nitrogen, natural gas, hydraulic, lubricating, and instrument air, including all tubing; and
  • The installation of all valves, valve trains pumps and instruments.

The electrical scope comprised the following activities:

  • The supply and installation of electrical equipment including MCCs, VFDs, DCS panels, UPS panels, distribution panels, transformers, junction boxes, control stations, lighting, disconnects, outlets, cable tray, instruments; and
  • The supply and installation of over 16,000 meters of cabling, including power and control cable, automation cable, instrumentation cable, heat trace, fiber optic, Ethernet cable; and
  • Termination and testing of all wiring. 

TESC successfully completed this project, achieving zero lost time injuries.

More Projects

Barrick Hemlo Cyanide Detox Plant & Tailings Flotation Complex
Glencore Onaping Depth Project Headworks Steel Installation
CKPI Installation of Chip Thickness Screening System
Domtar Power Recovery Boiler Chemical Treatment
Domtar HD Tower Piping
Coniston Generating Station 22kV-44kV Conversion
Mistinikon Lake Replacement of Spillway Guardrails and Flashboards
McVittie Generating Station Roof Replacement
Detour Gold Corporation Detour Lake Mine 13.8kV Substation Installation
Northgate Minerals Young Davidson Mine Substation Installation
BHP Billiton Jansen Mine Freeze Plant Supply Installation
Detour Gold Corporation Detour Lake Mine Concrete Slabs
Northgate Minerals Young Davidson Mine Headframe Construction
BHP Billiton Jansen Mine Hoist House Buildings
Vale No.8 Converter Installation
Sudbury INO Process Gas Project, Phase I
Mosaic K3 Mine Service Shaft Headframe Construction
Vale Matte Sep SMPEI Phase 2
Vale Matte Sep SMPEI Phase 1
Harte Gold Sugar Zone Mill Installation SMPEI Project
Tahoe Bell Creek Shaft Sinking Project
Sudbury Lime Plant Electrical Services Installation
Glencore Concentrate Unloading

Our portfolio

Project highlights showcasing TESC’s capabilities, problem solving, and leadership across industries.